Shopping Cart (0) items Sign In

Construction Claims Monthly - Devoted exclusively to the problems of construction contracting since 1963

‹ Prev article: 
 

No Pay For Extra Work Without Written Change Order

Friday, September 21, 2012 05:52 am

 

Conditions Precedent -- Change Order

Process Engineers & Constr., Inc. v. DiGregorio, Inc., 2012 R. I. Super. Lexis 112 (July 13, 2012)

A subcontractor's contract breach suit failed because several conditions precedent to payment on change orders had not been fulfilled. The sub did, however, prevail on its claim for additional costs associated with replacing a damaged pipe.

DiGregorio, Inc. (DiGregorio) was the excavation sub on a Brown University project to replace the underground piping system that delivers hot, high-pressure water to the university's heating plant. DiGregorio hired Process Engineers & Construction, Inc. (Process) to install the new pipe. Mid-project, sand infiltrated the heating plant after insulation surrounding one of the pipes was flooded at both ends. DiGregorio and Process replaced pieces of deteriorated pipe at a substantial cost, and the parties disputed who was responsible for the wet insulation. Process sued DiGregorio for contract breach, claiming that it had not been paid for changed work--and quantum meruit for replacing the damaged pipe.

The subcontract made plain (by incorporating by reference a standard AIA contract) that the pa [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team