Delay Damages

Wallace C. Drennan, Inc. v. City of New Orleans, 2011 La. App. Lexis 500 (4th Cir. Apr. 27, 2011)

Louisiana bid law prohibits a local government entity from sitting on an award until funding comes through without officially notifying the successful bidder of the delay. The City of New Orleans (City) awarded two publicwork contracts for street and utility renovation to Wallace C. Drennan, Inc. (Drennan) but then failed to execute the contracts within the statutory deadline. Drennan sued for delay damages, and it looks like it will get them.

Louisiana Public Bid Law requires a g [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team