Decisions Of The Comptroller General: Lost Bid Documents? Then You Lose, No Matter Whose Mistake.

Monday, April 11, 2011 11:01 am

 

Denied: Bid Bond

Matter of: Islands Mechanical Contractor, Inc., 2011 U.S. Comp. Gen. B-404275 (Jan. 24, 2011)

It may seem unfair, but when a government agency loses or misplaces information in your bid package, you're simply out of luck unless you can provide independent corroborating evidence for the bid's original contents.

Islands Mechanical Contractor, Inc. (IMC) submitted a bid for a U.S. Army Corps of Engineers' (Corps) a design/build project in the south Atlantic division. The solicitation required bidders to include an original bid guarantee and explained that facsimile or photo[...]

 