Sustained: Responsiveness

Matter of: Hostetter, Keach & Cassada Construction, LLC, 2010 U.S. Comp. Gen. B-403329 (Oct. 15, 2010)

A bidder's minor error in name should not have cost it the contract. Instead, the Comptroller General ruled the government should grant the contractor the award and pay for costs associated with its protest.

Hostetter, Keach & Cassada Construction, LLC (HKC) submitted the low bid on a Department of Veteran Affairs (VA) medical center construction project in Virginia. However, the VA reje [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team