17 Years Of Experience Don't Make Up For Poorly Detailed Bid

Thursday, December 02, 2010 01:31 am

 

Denied: Evaluation

Matter of: Hardiman Remediation Services, Inc., 2010 U.S. Comp. Gen. B-402838 Lexis 173 (Aug. 16, 2010)

A demolition contractor goofed by submitting a bid that described generic work rather than a site-specific plan. The Department of the Army, Corps of Engineers (Corps) in Huntsville, Alabama eliminated from competition the bid submitted by Hardiman Remediation Services, Inc. (Hardiman) to complete commercial demolition services under one of several fixed-price task order contracts. Hardiman protested, claiming the Corps unreasonably rated its bid unacceptable under the technical/management approach factor.

[...]
 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team