Decisions Of The Comptroller General: Losing Bid Includes The 'what' But Not The '

Friday, June 18, 2010 01:41 am

 

Denied: Bid Evaluation

Matter of: Dorado Services, Inc., 2010 U.S. Comp. Gen.B-402244 (Feb. 19, 2010)

An unsuccessful bidder protested its proposal's low rating, claiming it had more than "satisfactory" management/organization to support the project. But the contractor was not detail-oriented in complying with solicitation directions or requests.

Dorado Services, Inc. (Dorado) bid on an Army Corps of Engineers section 8(a), design-build project in Mobile, Alabama. Dorado's proposal earned similar scores to the eight bidd [...]

 