Denied: Bid Evaluation
Matter of: Dorado Services, Inc., 2010 U.S. Comp. Gen.B-402244 (Feb. 19, 2010)
An unsuccessful bidder protested its proposal's low rating, claiming it had more than "satisfactory" management/organization to support the project. But the contractor was not detail-oriented in complying with solicitation directions or requests.
Dorado Services, Inc. (Dorado) bid on an Army Corps of Engineers section 8(a), design-build project in Mobile, Alabama. Dorado's proposal earned similar scores to the eight bidd [...]