If The Govt. Can See Through Your Price Error, You Can Correct It

Friday, March 19, 2010 02:10 am

 

Denied: Bid Correction

Matter of: Prudent Technologies, Inc

., 2009 U.S. Comp.

Gen. Lexis 241, B-401736.3 (Dec. 9, 2009)

You can make a post-bid price correction if both the mistake and how it was made is obvious from the bid itself.

Prudent Technologies, Inc. claimed that the Environmental Protection Agency improperly allowed Environmental Restoration LLC (Environmental Restoration) to adjust its bid price after bid opening for an environmental remediation project. However, the government found "clear a [...]

 