Denied: Bidder Qualifications

Matter of: Solar Plexus, LLC

, 2009 U.S. Comp. Gen. B-

402061(Dec. 14, 2009)

Crying to the Comptroller General won't help you yank back an award to a bidder who hasn't complied with state laws, codes and regulations. Such compliance is a matter of contract administration, not award decis [...]