Shopping Cart (0) items Sign In

Construction Claims Monthly - Devoted exclusively to the problems of construction contracting since 1963

‹ Prev article: 
 

Failure To Properly Supervise Project Is An Error That Stings 10 Years Later

Friday, March 19, 2010 02:01 am

 

Contract Breach

Powers & Sons Construction Company, Inc. v. Healthy

East Chicago

, 2009 Ind. App. Lexis 2842 (Dec. 30, 2009)

A contractor's obligations to a project stem from the contract, so beware state statutes of limitation that allow contract breach claims many years after project completion.

Healthy East Chicago, Inc. (HEC) hired Powers & Sons Construction Company, Inc. (Powers) in December 1997 as the construction manager on a health services facility project in East Chicago, Indiana. After project completion in 1998, cracks appeared in the floors, walls and ceilings of the building. In 2000, Powers told HEC that "continuing concrete slab movement should be considered normal," and building inspections were conducted in 2002, 2004, 2005 and 2006. Finally, in 2007, HEC charged Powers with breach of contract. HEC claimed Powers knew or sho [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team