Sub Doesn't Pay For Contractor-caused Delay Even Though It Sub Doesn't Pay For Contracto

Monday, January 18, 2010 06:59 am

 

Delay - Damages

Arch Insurance Company v. Precision Stone, Inc., 2009 U.S. App. Lexis 21538 (Oct. 1, 2009)

Contractors: if you have to hire extra help so a sub can finish a job on time, don?t expect to take the extra cost out of the sub?s pay if you caused the delay. George A. Fuller Company (Fuller) hired Precision Stone Incorporated (Precision) as a subcontractor on a construction project in White Plains, New York. The City of White Plains had hired Fuller to build a plaza and fountain in time for Election Day, 2003. Precision agreed to perform the plaza?s stone work for $515,000, but the price did not include overtime work. Precisio[...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close