Shopping Cart (0) items Sign In

Construction Claims Monthly - Devoted exclusively to the problems of construction contracting since 1963

‹ Prev article: 
 

Sub Terminated For Failure To Complete On Time -- Or In 'reasonable Time'

Wednesday, December 30, 2009 03:52 am

 

Contract Interpretation -- Contract Termination

Int'l Production Specialists, Inc. v. Schwing America, Inc.

United States Court of Appeals for the Seventh Circuit

2009 U.S. App. Lexis 19842 (September 2, 2009)

If a contract doesn't specifically include performance deadlines, work must be completed within a reasonable amount of time. But you don't have a "reasonable time" contract just because you disagree on the schedule.

Subcontractor Schwing American, Inc. (Schwing) hired manufacturer International Production Specialists, Inc. (IPS) to fabricate and install five storage silos at a wastewater treatment plant owned by Illinois' North Shore Sanitary District. While the original project timeline was eight months, the project was incomplete after more than three years. Schwing terminated IPS's contract citing IPS's failure to complete timely and satisfactory work. IPS sued for contract breach and Schwing countersued.

A district court found in Schwing's favor, and that verdict stood on appeal. [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team