Pay Measurement Excluded Certain Fill Unit Prices; Payment

Saturday, July 09, 2005 03:19 pm

 

The Armed Services Board of Contract Appeals has ruled that a specification excluded certain fill from the unitprice pay measurement.

The Corps of Engineers awarded a unit-price contract to CKY, Inc. for rehabilitation of a levee. One contract line item covered stone protection pieces. Another item covered embankment soil fill. A specification said payment was to be made by the cubic yard for fill placed " [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team