Shopping Cart (0) items Sign In

Construction Claims Monthly - Devoted exclusively to the problems of construction contracting since 1963

‹ Prev article: 
 

Contractor's Early Completion Claim Denied Schedule; Interference

Thursday, June 09, 2005 03:00 pm

 

The Armed Services Board of Contract Appeals has ruled that a prime contractor could not recover on behalf of a subcontractor for government interference with scheduled early completion. The contractor did not base its own work on that schedule and the schedule was not feasible.

The Army Corps of Engineers awarded a contract to Fru-Con Construction Corp. for rehabilitation of a dam on the Ohio River near Gallipolis, West Virginia. The contract allowed five years for completion of the work. Fru-Con submitted a proposed project schedule which utilized the full five years, installing eight new roller gates on a "1-2-2-2-1"annual basis. The government approved this schedule.

Fru-Con subcontracted the fabrication and installation of the new roller gates to Noell, Inc. A Noell employee prepared a suggested installation sequence which reflected a three-year "2-3-3"schedule. This proposed schedule was submitted to Fru-Con. The prime contractor approved it c [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team