Acceleration Claim Barred By Lack Of Notice Acceleration; Notice

Thursday, June 09, 2005 03:00 pm

 

An Indiana court has ruled that a contractor's claim for acceleration of its work was barred by the failure to comply with the contractual notice requirement. The Taylor Community Schools Building Corporation was expanding and renovating a high school building. Taylor awarded a contract for the electrical work to Stelko Electric, Inc.

The parties utilized a modified version of AIA Document A201, "General Conditions of the Contract for Construction."One provision, unchanged from the AIA contract form, stated: "Claims by either party must be made within 21 days after occurrence of the event giving rise to such Claim or within 21 days after the c [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team