Contractor Responsible For Pre-bid Soil Investigation Differing Site Conditions-subsurface

Thursday, June 09, 2005 03:00 pm

 
Contractor Responsible For Pre-bid Soil Investigation Differing Site Conditions-subsurface

An Ohio court has ruled that a project owner did not withhold information regarding groundwater at the site. And the contract documents made bidders responsible for conducting their own subsurface investigations.

The City of Troy was planning an extension of its sewer system. Much of the new line was to be installed under an existing roadway. The City's consulting engineer said shallow groundwater might be present in the area, but the City's agreement with the engineer expressly excluded the performance of any test borings. The City issued an invitation for bids. [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close