Contractor Sues Cm Over Master Schedule Schedule; Negligence

Monday, May 09, 2005 02:51 pm

 
Contractor Sues Cm Over Master Schedule Schedule; Negligence

A federal district court has ruled that a trade contractor could maintain an action against a construction manager (CM) for failure to incorporate milestone dates into a master project schedule, but only if the CM had exerted "excessive control" over the contractor.

The Perrysburg Exempted Village School District retained Rudolph/Libbe, Inc. to serve as CM for the construction of a new high school building. Riverside Masonry, LLC was preparing to bid on the masonry work.

The bid documents, furnished by the District, included scheduling milestone dates. The m [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team