Change Order Requirement Waived At Meetings Changes-directed; Waiver

Monday, May 09, 2005 02:51 pm

 
Change Order Requirement Waived At Meetings Changes-directed; Waiver

A Minnesota court has ruled that a project owner waived a written change order requirement by orally directing changes at project meetings.

West Bloomington Motel, Inc. (WBM) awarded a design/build contract to Vanman Companies Architects and Builders for renovation of a motel property. When the design phase was complete, the parties signed a fixedprice "Part 2 Agreement" for the construction work. The agreement included the following provision.

"This Part 2 Agreement represents the entire agreement between the Owner and the Design/Builder and supersedes prior neg [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team