Drawing Narrowed Spec But Did Not Conflict Plans And Specifications; Changes-constructive

Monday, May 09, 2005 02:51 pm

 
Drawing Narrowed Spec But Did Not Conflict Plans And Specifications; Changes-constructive

The Armed Services Board of Contract Appeals has ruled that where a specification stated multiple options and a drawing detail narrowed the contractor's options, there was no conflict and the specification did not supersede the drawing detail.

The Army Corps of Engineers awarded a contract to Medlin Construction Group, Ltd. for construction of a vehicle maintenance facility at Fort Hood, Texas. The [...]

 