No Postponement Of Notice-to-proceed Delay-nonexcusable

Saturday, April 09, 2005 02:40 pm

 
No Postponement Of Notice-to-proceed Delay-nonexcusable

The General Services Administration Board of Contract Appeals has upheld a termination for default due to failure to commence work. The contractor had not been entitled to postponement of issuance of the notice-toproceed.

The GSA awarded a contract to NECCO, Inc. to replace the roof of th [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team