Change Order Work Was Unit Priced Unit Prices; Acceptance

Saturday, April 09, 2005 02:40 pm

 
Change Order Work Was Unit Priced Unit Prices; Acceptance

A federal appeals court has ruled that extra work was ordered on a unit-price, not fixed-price, basis. And the government was entitled to revoke final acceptance in order to recover an overpayment from the contractor.

The U.S. Army awarded a fixed-price contract to Bender GmbH to clean and close a sewage treatment plant in Babenhausen, Germany. The scope of work included the removal and disposal of water and sludge in several tanks at the facility.

After contract award, the Army learned that the sludge was contaminated with heavy [...]

 