Purchase Order Did Not Govern Transaction Suppliers; Schedule

Wednesday, March 09, 2005 01:13 pm

 
Purchase Order Did Not Govern Transaction Suppliers; Schedule

A federal appeals court has ruled that a contractor's purchase order and its delivery schedule did not govern a transaction with a material supplier.

Crossley Construction Corp. was the general contractor on a commercial construction project in Gatlinburg, Tennessee. Crossley's original metal roofing supplier was unable to provide sufficient materials in time for Crossley to meet its completion deadline. Crossley contacted NCI Building Systems, a metal fabricator and supplier located in Houston.

A Crossley representative sent NCI a purchase ord [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team