Deficient Work Not Specifically Referenced Termination-default

Wednesday, March 09, 2005 01:13 pm

 
Deficient Work Not Specifically Referenced Termination-default

The Department of Agriculture Board of Contract Appeals has reversed a default termination because the contracting officer, while citing deficient work, failed to reference the specifications from which the contractor had deviated.

The U.S. Forest Service awarded a contract to Trinity Installers, Inc. to remove an existing roof on a machine shop in the Gifford Pinchot National Forest in Oregon and replace it with a metal roo [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team