Bid Nonresponsive Due To Inadequate Subcontracting Efforts Bids-responsiveness; Subcontractors

Wednesday, February 09, 2005 01:02 pm

 
Bid Nonresponsive Due To Inadequate Subcontracting Efforts Bids-responsiveness; Subcontractors

A Pennsylvania court has ruled a bid nonresponsive because the bidder did not make adequate efforts regarding solicitation and participation of minority business enterprise and women business enterprise (MBE/WBE) subcontractors.

The Pennsylvania Department of General Services issued an invitation for bids for construction of a welcome center in Erie. The IFB required, in accordance with an Executive Order, that bidders solicit quotations from a minimum number of certified MBE/WBE subcontractors and suppliers.

The IFB required bidders to furnish evidence [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team