Sub Could Be Held To Quote Despite Known Mistake Bids-mistakes; Equitable Relief

Wednesday, February 09, 2005 01:02 pm

 
Sub Could Be Held To Quote Despite Known Mistake Bids-mistakes; Equitable Relief

A California court has ruled that a prime contractor could hold a listed subcontractor to its quoted price even though the sub informed the prime of a mistake before execution of a contract with a public project owner.

The City of Livermore solicited bids for renovation of its city hall. Diede Construction, Inc. was preparing to bid on the contract and received a price quotation for the mechanical work from Monterey Mechanical Co. Diede incorporated that price into its estimate, listed Monterey as its mechanical subcontractor, and submitted the low bid.

Three days after bid op [...]

 