Concurrent Delay Subsumed By Contract Modification Delay-compensable; Release

Wednesday, February 09, 2005 01:02 pm

 
Concurrent Delay Subsumed By Contract Modification Delay-compensable; Release

The Armed Services Board of Contract Appeals has ruled that a bilateral contract modification for a no-cost extension of time due to late delivery of construction documents subsumed another government-caused delay which was concurrent. But the contractor was allowed to pursue a third claim for delay which was not clearly concurrent.

The Army Corps of Engineers awarded a contract to Wescorp, Inc. for construction of a golf course clubhouse at Pope Air Force Base in North Carolina. The contract required Wescorp to commence work w [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close