Shopping Cart (0) items Sign In

Construction Claims Monthly - Devoted exclusively to the problems of construction contracting since 1963

‹ Prev article: 
 

Sub Suffers 3 Strikes In Attempt To Exploit No-damage-for-delay Exceptions

Tuesday, November 04, 2008 04:03 pm

 
Sub Suffers 3 Strikes In Attempt To Exploit No-damage-for-delay Exceptions

A subcontractor frustrated by project stops and starts tried to argue its way toward more than $300,000 in delay damages. But New York generally upholds no-damage-fordelays clauses, and a state supreme court stood firm in the face of both fraud allegations and three exception-to-therule arguments.

Premier-New York Inc. (Premier) subcontracted with Trataros Construction, Inc. (Trataros) to perform roofing work on a project at Baruch College in New York City. In drafting its bid, Premier relied on a sample CPM scheduleincluded with the subcontract documents. The actual project work, however, did not adhere to that schedule, and, as a result, Premier claimed it suffered delays and increased costs due primarily to work re-sequencing and lack of accessibility to key facilities. Premier argued that it would have submitted a higher price bid if it had been informed of the actual project circumstances. Trataros countered that the subcontract's no-damage-for-delay clause barred Premier from any recovery to make up for that alleged error -- and the court agreed.

At trial, Premier was up against unambiguous, clearly stated subcontract language that: a) described the CPM schedule as only a "sample," which was already seven months old by the time of contractor- subcontractor negotiations; b) warned that the subcontractor might be required to work out of sequence; c) required that Premier conduct an independent review of the project and take responsibility for acquiring any pertinent information about project status before entering the subcontract.

Plus, a no-damage-for-delay clause waived Premier's right to additional compensation for work hindered by delays, disruptions or [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team