When Time Is Of The Essence, Govt. Need Not Seal Its Bids

Sunday, May 04, 2008 02:48 pm

 
When Time Is Of The Essence, Govt. Need Not Seal Its Bids

A protester's claim that the government violated the Competition in Contracting Act (CICA) by using negotiat-ed procedures instead of sealed bidding fell flat since completion of the project, intended to control flooding in an area hit by Hurricane Katrina, took precedence.

Under CICA, an agency must use sealed bidding when: (1) time permits, (2) the award will be based on price and other price-related factors, (3) discussions are not necessary and (4) more than [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team