Shopping Cart (0) items Sign In

Construction Claims Monthly - Devoted exclusively to the problems of construction contracting since 1963

‹ Prev article: 
 

Suspension Determinacy Questioned In Establishing Standby Requirement For Eichleay

Thursday, October 04, 2007 12:52 pm

 
Suspension Determinacy Questioned In Establishing Standby Requirement For Eichleay

A court ruled that the existence of a letter indicating a specific time period for a government-ordered contract suspension is not enough to prove that the suspension was for a definite period -- thus opening the door for possible recovery of unabsorbed home overhead expenses under the Eichleay formula (a formula for calculating such expenses based on 60-2 B.C.A. (CCH) P2688 (ASBCA 1960)).

In September 2002, the government awarded Oak Environmental Consultants, Inc. (Oak) a contract to repair naval station housing. After work began, the government suspended the project at its convenience, as allowed by the contract, because of possible plans for demolition and privatization of the property. The letter informing Oak of the suspension described the suspension as being fo [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team