Shopping Cart (0) items Sign In

Construction Claims Monthly - Devoted exclusively to the problems of construction contracting since 1963

‹ Prev article: 
 

Milestone Documentation Proves Key In Default Termination Case

Thursday, October 04, 2007 12:52 pm

 
Milestone Documentation Proves Key In Default Termination Case

The Armed Services Board of Contract Appeals ruled that a default termination by the government was justified according to the contract because the contracting officer was "justifiably insecure about the contract's timely completion."

Default termination is generally viewed as an extreme measure, requiring a substantial burden of proof on the party terminating the contract. This case sheds light on the kinds of actions that may lead to default termination, as well as the documentation that may be used to either uphold or challenge the termination in court.

Default termination allowed when party is justifiably insecure about completion

In September 1998, the Army Corps of Engineers (Corps) awarded FFR-Bauelemente + Bausanierung GmbH (FFR) a contract to restore a military barracks building. The Corps e [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team