Shopping Cart (0) items Sign In

Construction Claims Monthly - Devoted exclusively to the problems of construction contracting since 1963

‹ Prev article: 
 

Subcontractors: Have Lien Waivers, Insurance Certificates On Hand In Case Of Dispute

Tuesday, September 04, 2007 12:42 pm

 

AWisconsin court affirmed a judgment allowing a contractor to withhold funds set aside for pending vendor claims where the contract explicitly authorized the contractor to do so. The subcontractor's failure to complete work triggered a warning notice and, ultimately, termination.

The Milwaukee Metropolitan Sewerage District (the district) contracted with Kenny Construction Company (Kenny) to work on a street rehabilitation project. Kenny subcontracted with Dionne Construction and Traffic Company (Dionne) to rehabilitate approximately 52 manholes pursuant to the project. Dionne agreed to prepare, coat and seal each manhole to the satisfaction of the district in return for payment.

By the subcontract's terms, Kenny could terminate the subcontract if Dionne "defaulted in the performance of any its conditions." If Dionne failed to perform, the contract authorized Kenny to "retain out of any monies . . . due the Sub-contractor a sum sufficient to pa [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team