Contractor Learns That A Restroom's Color Is Amaterial Requirement

Monday, June 04, 2007 12:21 pm

 
Contractor Learns That A Restroom's Color Is Amaterial Requirement

A bidder's failure to acknowledge an amendment to the government's invitation for bids (IFB) -- which

changed the exterior color of a restroom facility -- rendered the bid nonresponsive and cost the contractor a deal with the Department of Transportation.

The Federal Highway Administration (FHA) issued an IFB for resurfacing, grading, drainage and pavement reconstruction of Head of the Meadows Beach [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team