Builder Not Entitled To 'unforeseeable Costs' Of Construction In Post Office Construction Contract

The Postal Service Board of Contract Appeals held that a lessor bore the risk "that local permitting authorities would impose conditions to granting necessary construction permission that would increase its costs of construction."

Baer Real Estate (Baer) contracted with the United States Postal Service (USPS) to build a post office meeting USPS's specifications and lease it back to USPS. After unsuccessfully n [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team