Subcontractor Loses Attempt To Bypass Mediation Requirements Subcontractors

A federal district court judge required that a subcontractor abide by all of the subcontractor's terms and exhaust all of its remedies before filing a lawsuit against the contractor.

The University of Kansas Hospital Authority (Owner) entered into a contract with United Excel Corporation (UEC) for improvements to the central utility plant at the university's medical center (prime contract). UEC subcontracted with U.S. Engineering Company, Inc. to provide labor, materials, equipment and supervision of the mechanical systems' installation.

On May 16, 2006, U.S. Engineering submitted a claim to UEC based on UEC's failure to respond to its requests for information or clarification related to the drawings and specifications, which U.S. Engineering said were incomplete, vague and incorrect.

After waiting five mont [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team