Cost Overruns In Excess Of Retainage Leave Subcontractor Empty-handed

Sunday, March 04, 2007 11:37 am

 
Cost Overruns In Excess Of Retainage Leave Subcontractor Empty-handed

An Indiana appeals court rejected a subcontractor's argument that retainage the State held did not belong to the State but to the general contractor.

The State of Indiana (State) hired Voils Construction to make improvements to the visitor center at Mounds State Park in Anderson, IN. Voils subcontracted the tile and carpet work to CCI. Between October 2001 and May 2002, CCI submitted four payment requests to Voils totaling $35,450. Voils paid CCI a total of $15,000.

In November 2002, [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team