Contractor Will Not Receive Compensation For Change Order Cost Increases

Sunday, February 04, 2007 11:30 am

 
Contractor Will Not Receive Compensation For Change Order Cost Increases

The Armed Services Board of Contract Appeals recently denied a contractor's motion for reconsideration of its decision to grant summary judgment to the Army Corps of Engineers (Corps).

In June 2004, the Corps and Tillamook County, Oregon asked the Oregon Parks and Recreation Department (OPRD) for permission to perform work on the North Jetty Revetment at Tillamook Bay. The OPRD approved the application and issued a revetment permit. The permit, however, included several conditions. One of those stated that the permittees "shall place sand brought in from off-site in front of [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team