Price Proposal Not Deadline Nixed Bidder's Proposal

Thursday, January 04, 2007 11:21 am

 
Price Proposal -- Not Deadline -- Nixed Bidder's Proposal

The Comptroller General ruled that the Marine Corps properly rejected a late final proposal request from a bidder because the bidder's price proposal was not competitive as compared to the winning bid.

The U.S. Marine Corps awarded a contract to integrate, produce and document the Tactical Data Network Data Distribution System-Replacement production mo [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team