Evaluation Factor Inferred Bids

Sunday, June 04, 2006 10:59 am

 
Evaluation Factor Inferred Bids

The Comptroller General has ruled that a technical evaluation factor, while not expressly stated in the solicita-tion, was reasonably encompassed in the overall evalua-tion scheme.

The Army Corps of Engineers issued a request for proposals for improvements to the Bluestone Dam in Hin-ton, West Virginia. The work consisted primarily o [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team