Stated Assumption Did Not Alter Drawing Note Changes-constructive; Plans And Specifications

Monday, April 03, 2006 06:08 pm

 
Stated Assumption Did Not Alter Drawing Note Changes-constructive; Plans And Specifications

The Armed Services Board of Contract Appeals has ruled that an offeror's stated assumption in a technical proposal did not negate or supersede a clear note on a contract drawing.

The Army Corps of Engineers issued a request for proposals for design and construction of a munitions maintenance facility at Nellis Air Force Base in Nevada. The site map included a note stating that no borrow or spoil [...]

 