Bidder Nonresponsibility Determination Upheld Bids-responsibility

Monday, April 03, 2006 06:08 pm

 
Bidder Nonresponsibility Determination Upheld Bids-responsibility

A Wisconsin court has allowed a municipality to escape unscathed despite the mishandling of the bidder responsibility determination process.

The Town of Pittsfield solicited bids for four separate road improvement projects. D.M.K., Inc. submitted the low bid on each of the four contracts. Town officials and their consulting engineer expressed concern about D.M.K. due to problems they had experienced with the contractor on prior projects.

The town chairperson said she would like to rebuild confidence in D.M.K., but didn't think the contractor was capable of perform [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team