Shopping Cart (0) items Sign In

Construction Claims Monthly - Devoted exclusively to the problems of construction contracting since 1963

‹ Prev article: 
 

No Liquidated Damages After Substantial Completion Liquidated Damages; Substantial Completion

Friday, March 03, 2006 05:24 pm

 
No Liquidated Damages After Substantial Completion Liquidated Damages; Substantial Completion

A Louisiana court has ruled that a project owner could not assess liquidated damages after a contractor had achieved substantial completion and was performing only punch list work.

The Mansfield Housing Authority awarded a contract to All Seasons Construction, Inc. to re-roof and replace the fascia and soffits on 28 duplex buildings. The contract required the work to be substantially complete within 120 calendar days of issuance of notice-to-proceed, with the contractor subject to liquidated damages of $200 per day for late completion.

Whe [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team