Claim Not Cut Off By Unilateral Final Payment Payment-final

The Armed Services Board of Contract Appeals has ruled that an agency cannot cut off a claim by unilaterally paying the outstanding contract balance.

The Corps of Engineers awarded a contract to JT Construction Co., Inc. to construct a building at Kelly Air [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team