Owner Lost Right To Assess Liquidated Damages Liquidated Damages; Schedule

Friday, March 03, 2006 05:24 pm

 
Owner Lost Right To Assess Liquidated Damages Liquidated Damages; Schedule

A federal appeals court has ruled that a private project owner waived a completion deadline and lost the right to assess liquidated damages by allowing construction to continue without setting a new deadline.

RDP Royal Palm Hotel, L.P. awarded a contract to Clark Construction Group, Inc. to construct a hotel in Miami Beach, Florida. The contract called for substantial completion within 518 calendar days, with liquidated damages to be assessed for late completion. Clark guaranteed a maximum price, but both the price and the completion deadline were to be adjusted to account for ch [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close