Owner Lost Right To Assess Liquidated Damages Liquidated Damages; Schedule

Friday, March 03, 2006 05:24 pm

 
Owner Lost Right To Assess Liquidated Damages Liquidated Damages; Schedule

A federal appeals court has ruled that a private project owner waived a completion deadline and lost the right to assess liquidated damages by allowing construction to continue without setting a new deadline.

RDP Royal Palm Hotel, L.P. awarded a contract to Clark Construction Group, Inc. to construct a hotel in Miami Beach, Florida. The contract called for substantial completion within 518 calendar days, with liquidated damages to be assessed for late completion. Clark guaranteed a maximum price, but both the price and the completion deadline were to be adjusted to account for ch [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team