Payment Scheme Cannot Negate Site Conditions Clause Differing Site Conditions-subsurface

The Armed Services Board of Contract Appeals has ruled that the government's interpretation of a rock excavation payment provision could not stand if it abrogated the standard Differing Site Conditions clause.

The Corps of Engineers issued a solicitation for construction of family housing units at Mountain Home Air Force Base in Idaho. The contract documents included detailed geotechnical information, but cautioned that: "The enclosed geotechnical survey logs of exploration are provided for prop [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close