Notice Requirements Varied With Type Of Claim Notice; Claims Administration

Tuesday, January 03, 2006 05:03 pm

 
Notice Requirements Varied With Type Of Claim Notice; Claims Administration

The Oklahoma Supreme Court has ruled that standard state specifications contained different notice requirements which applied to different types of claims. A single notice did not preserve all claims.

The Oklahoma Transportation Authority awarded a contract to M. J. Lee Construction Co. for bridge construction in the Tulsa area. Work was significantly delayed due to the failure of a separate lead contractor to complete its assignment in a timely manner. Lee submitted a formal claim for $655,040 in delay damages. The delay claim proceeded through a multi-tier admin [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team