Prime Delays Sub's Installation With Impunity Schedule; Subcontractors

Tuesday, January 03, 2006 05:03 pm

 
Prime Delays Sub's Installation With Impunity Schedule; Subcontractors

A New York court has ruled that a prime contractor was entitled to postpone a subcontractor's commencement of its installation work with no liability for delay damages.

Sweet Associates, Inc. was the prime contractor on a building project. Sweet awarded a subcontract to Modern Mosaic, Ltd. to fabricate and install approximately 500 precast concrete panels for the exterior of the building.

The subcontract stated that Modern Mosaic would perform its work "in accordance with the project schedule developed by Sweet."The subcontract also gave Sweet the right, without limitation, to make changes in the [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team