Request For Adjustment Was Not A "Claim" Claims Administration

The Armed Services Board of Contract Appeals has ruled that a contractor's request for an equitable adjustment (REA) was not a "claim" within the meaning of the Contract Disputes Act.

The Army Corps of Engineers awarded a contract to Engineered Demolition, Inc. (EDI) for demolition of flood control structures on the Napa River in California. [...]

 