Termination Settlement Proposal Not Timely Termination-convenience

Saturday, December 03, 2005 04:41 pm

 
Termination Settlement Proposal Not Timely Termination-convenience

The Armed Services Board of Contract Appeals has ruled that when a default termination is converted to a termination for the convenience of the government, the contractor must submit a termination settlement proposal within one year of notification of the conversion.

The Army awarded a contract to Ryste & Ricas, Inc. (R & R) for renovation of a building at Fort Belvoir, V [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team