Subcontractor Punished For Payment Deal Subcontractors; Payment

A Missouri court has upheld a punitive damage assessment against a subcontractor that went over the prime contractor's head to recover payment directly from the project owner.

St. Johns Regional Medical Center awarded a contract to Environmental Energy Partners, Inc. (EEP) for extensive renovation of a facility. EEP subcontracted the HVAC work to Siemens Building Technologies, Inc. The subcontract called for EEP to make periodic payments to Siemens as the prime contractor received payment from the project owner for Siemens' work.

At the conclusion of the project, the [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team