Financial Data Not Consistent With Eichleay Formula Delay-damages; Overhead

Saturday, December 03, 2005 04:41 pm

 
Financial Data Not Consistent With Eichleay Formula Delay-damages; Overhead

The U.S. Court of Federal Claims has ruled that while a contractor had established entitlement to unabsorbed home office overhead, the contractor's financial data did not comport with the proper use of the Eichleay formula.

The Navy awarded a contract to Orlosky, Inc. to replace high voltage circuit breakers and to perform a coordination study of the electrical system at a weapons center on San Nicholas Island off the coast of California. The contract called for completion in 200 calendar days.

Orlosky experienced a series of government-caused delays involving lack of power out [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team