No Deductive Credit For Reduced Bond Premium Changes-deductive; Bonds

Thursday, November 03, 2005 04:23 pm

 
No Deductive Credit For Reduced Bond Premium Changes-deductive; Bonds

The General Services Administration Board of Contract Appeals has ruled that the government could not take deductive credits from fixed-price contracts based upon lower than expected bond premiums.

The GSA negotiated two contracts with Pangea, Inc. for replacement of roofs on federal buildings in St. Louis. Pangea submitted proposals breaking down its costs to a certain extent. The GSA questioned some of the costs, including the bond premiums. Pangea said it did not yet know the actual premiums, and the figures were merely estimates. At the con [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team